Projects and WBS Codes
Each cost sits on a project and a WBS code, such as 09-200 Drywall with the cost type Subcontract. Procore's connector turns every budgeted code into a QuickBooks Service item named project-cost code.cost type, such as 2417-09-200 followed by the cost type, which is why single-tier cost codes cannot sync.